|
The judgment of the
House of Lords in Transfield Shipping Inc v Mercator Shipping Inc (The
Achilleas) [2008] UKHL 48 considered the law on recoverable damages
following a breach of contract. Although all members of the House were
in agreement as to the outcome of the appeal on the facts, there were
differences in the reasoning. The way in which the case is interpreted
going forwards and, in particular, the reasoning that is adopted, will
play an important role in the law of contractual damages.
The Facts
By a time charter dated 22 January 2003, the appellant, Transfield
Shipping Inc ("Transfield") chartered a vessel from Mercator Shipping
Inc ("Mercator") at a daily rate of US$13,500 for a period of five to
seven months. By an addendum dated 12 September 2003, the vessel was
chartered for a further five to seven months at a daily rate of
US$16,750 with the latest date for redelivery set at 2 May 2004.
On 20 April 2004, Transfield gave notice of redelivery between 30 April
and 2 May 2004. Mercator fixed a new four to six month charter with a
third party which, due to prevailing market conditions, was at a daily
rate of US$39,500. The latest date for delivery to the third party
charterer was 8 May 2004.
Less than two weeks before 2 May 2004, Transfield sub-chartered the
vessel. Due to delays outside of the control of Transfield, the vessel
was not redelivered until 11 May 2004. By that time, charter market
rates had fallen and Mercator agreed with the third party charterer to
reduce the daily rate in the new charter to US$31,500 in return for the
third party charterer agreeing to extend the cancellation date to 11 May
2004.
Mercator claimed from Transfield the US$8,000 per day difference between
the daily rate it originally agreed with the third party charterer and
the amended daily rate it agreed due to the late redelivery of the
vessel. The sum claimed totalled US$1,364,584.37. Transfield submitted
that the claim should be limited to the difference between the market
rate and the charter rate for the nine day period during which Mercator
could not use the vessel. The alternative sum totalled US$158,301.17.
Decision of Arbitrator, High Court and Court of Appeal
The claim went first to arbitration where by a two to one majority, the
tribunal allowed Mercator's claim in full. First Mr Justice Christopher
Clarke and then a Court of Appeal composed of Lord Justice Ward, Lord
Justice Tuckey and Lord Justice Rix upheld the majority arbitral award.
The Issue on Appeal
The question before the House of Lords is summarised in the judgment of
Lord Hoffmann as follows:
"is the rule that a party may recover losses
which were foreseeable ("not unlikely") an external rule of law,
imposed upon the parties to every contract in default of express
provision to the contrary, or is it a prima facie assumption about
what the parties may be taken to have intended, no doubt applicable
in the great majority of cases but capable of rebuttal in cases in
which the context, surrounding circumstances or general
understanding in the relevant market shows that a party would not
reasonably have been regarded as assuming responsibility for such
losses?"
In short, could the House of Lords move beyond the
Hadley v Baxendale (1854) 9 Exch 341 and The Heron II [1969] 1 AC 350
line of authority based on foreseeability and consider any limitations
on recoverable damages?
Judgment of the House of Lords
The House of Lords unanimously allowed the appeal and Mercator were
restricted in its recovery to the difference between the market rate and
the charter rate for the period during which it was prevented from using
the vessel by the delay in its redelivery. All five of the Appellate
Committee gave a reasoned judgment, and different schools of thought can
be detected in the judgments as regards the reasons for allowing the
appeal.
Assumed Responsibility - Lord Hoffmann and Lord Hope
Lord Hoffman and Lord Hope opined that the appropriate test was not
simply to determine whether the loss was one which was not unlikely.
Rather, it was to ascertain the scope of the obligations for which the
contractor could reasonably be expected to have assumed responsibility
for. Although the charter of the vessel to a third party charterer and
the fluctuation of market values were "not unlikely", these were not
losses for which Transfield assumed responsibility. Lord Hoffmann and
Lord Hope gave several reasons for that conclusion:
-
Although it would be considered likely that
Mercator would enter into a future charter, the risk was
unquantifiable as, at the time of the charter to Transfield, neither
party would have any idea about when the further charter would be
entered into, its length or other terms.
-
Mercator could have rejected Transfield's orders
for the final charter had it been clear to the Mercator that the
last charter was bound to overrun. It did not do so and the final
charter was a legitimate use of the vessel which, but for
circumstances beyond the control of Transfield, would not have
resulted in late delivery.
-
The charter market has proceeded for a number
years on the basis that the correct damages calculation for late
redelivery of a vessel was the difference between the market rate
and the charter rate for the period of late delivery. Lord Hoffmann
referred to several authorities in support of that point.
-
If Transfield had intended to and been aware of
an obligation to assume a liability for the type of damages claimed
by Mercator, Transfield could have negotiated with Mercator a
discount for assuming that risk.
Matters in Contemplation of the Parties - Lord
Rodger and Baroness Hale
Although both Lord Rodger and Baroness Hale allowed the appeal, both,
and in particular Baroness Hale, did so on a slightly narrower ground.
In a steady or rising charter party market, the claim by Mercator would
never have arisen. It is assumed in the market that there will usually
be adequate demand for chartered vessels and that, should a late
redelivery take place, the owner will be able to fix a charter with a
third party without loss, even if it loses a pre-arranged charter due to
the late redelivery. Therefore, the only loss would be the difference
between the market rate and the charter rate for the period of
redelivery.
In the current case, it was only because the market was extremely
volatile, with the value of the charter daily rate falling US$8,000 (or
approximately 20%) over a very short period. That volatility created the
additional loss in relation to a third party contract that Transfield
knew nothing about. The loss was not one for which Lord Rodger and
Baroness Hale would hold Transfield to be liable. As Baroness Hale
stated, "It is one thing to say… that missing dates for a subsequent
fixture was within the parties' contemplation as "not unlikely". It is
another thing to say that the "extremely volatile" conditions which
brought about this particular loss were "not unlikely"." That
reasoning, therefore, would continue the foreseeability test of Hadley v
Baxendale and The Heron II.
The difference in the judgments of Lord Rodger and Baroness Hale is
that, although Lord Rodger states that he does not find it necessary to
explore the question of assumption of responsibility considered by Lord
Hoffman, he does state that he is "otherwise in substantial agreement
with [Lord Hoffman's] reasons". By contrast, Baroness Hale
expressed her hesitance to follow the assumption of responsibility
reasoning, preferring to leave such considerations for future cases.
Nature and Object of the Contract – Lord Walker
Lord Walker considers the assumption of responsibility test, but neither
endorses nor rejects it explicitly. The test Lord Walker appears to
prefer is the "question of what the contracting parties must be taken
to have had in mind, having regard to the nature and object of the
business transaction". Although, perhaps, a slight development on the existing
line of case law, such a test would not seem to go as far as that
expounded by Lord Hoffmann. Having said that, Lord Walker concludes his
judgment with "For these reasons, and for the further reasons given
by my noble and learned friend Lord Hoffmann, Lord Hope and Lord
Rodger…I would allow this appeal".
Comment
On one reading, the case continues Lord Hoffman's reformulation of
recoverable damages commenced with the seminal SAAMCO case (South
Australia Asset Management Corp v Young Montague Ltd [1997] AC 191). In
SAAMCO, Lord Hoffmann, giving the only judgment, with which there was
unanimous agreement in the House, held that in the professional
negligence context, a Claimant could only recover from a Defendant
damages that fall within the scope of the duty owed by the Defendant to
the Claimant. The agreement must be construed as a whole in its
commercial setting. If that reasoning is adopted, Transfield v Mercator
may extend that principle into a wider contractual field.
On an alternative reading, the effect of the case is not nearly as
dramatic. There were only two Law Lords that specifically adopted the
assumption of responsibility test (although Lord Walker's "nature and
objects" test could be seen as similar to the SAAMCO construction test)
with Baroness Hale fiercely critical of any such principle. Further, the
facts of the case were very specific. It is customary in the charter
party market that the only damages that are recoverable are calculated
by reference to the difference between the market rate and the charter
rate for the period of late delivery; the final sub-charter that led to
the late delivery was a legitimate contract for which there was adequate
time and about which Mercator could have objected if it felt there was
not adequate time; the late delivery was due to circumstances outside of
Transfield's control; and the only reason there was a claim (or at least
a claim of such magnitude) was because of the volatility of the charter
party market at that time.
Even Lord Hoffmann made clear that the traditional test for recoverable
damages of Hadley v Baxendale and The Heron II would be the starting
point and that the assumption of responsibility test should only be used
where the circumstances require it. It remains to be seen, therefore,
whether Transfield v Mercator has any significant practical impact on
the law of recoverable contractual damages.
The law on contractual damages is, of course, subject to the express
agreement of the contracting parties. It would have been open to the
charter parties to agree that the charterer would be liable to the owner
for loss of profit on future fixtures as a result of late delivery.
Indeed, Lord Hoffmann's test is concerned to discover the intention of
the parties in that regard. Therefore, if there is a particular head of
loss about which a party is concerned to pass on potential liability to
a counterparty, there is no impediment to making specific agreement to
that effect.
To subscribe or unsubscribe
To enquire about further publications, or to unsubscribe from this e-bulletin, please email
Sally
Whittaker, or visit the Herbert Smith website
here. |
The content of this article does not constitute legal advice and should not be relied on as such. Specific advice should be sought about your specific circumstances.
Herbert Smith LLP, Gleiss Lutz and Stibbe are three independent firms
which have a formal alliance.
© Herbert Smith LLP 2008

|
|
|